Project Description
Design and construct a pathway on Marathon Boulevard.Project Location
Marathon Boulevard from Gasparilla Road (CR771) to the Cape Haze Trail crossing.Latest Updates
This project is being joined with the Sunset Blvd. E. Sidewalk project for construction.
The contractor has completed work and received substantial completion they are now finishing up punch list items to complete the project.
Budget
Phase | Cost |
---|---|
Design | $43,295.00 |
Construction | $166,750.00 |
Total Budget | $210,045.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/14/2021 | 11/30/2021 | |
Design Development | 02/02/2022 | 12/03/2022 | |
Construction | 08/02/2023 | 01/29/2024 |
Project Phase
Construction
Last Updated
04/29/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD